I suppose that membrane for roofing does not need to be so strong as that designed for walls as the latter has to support its own weight completely but realistically, for a single storey structure and careful owner-builder use, I cant image there would be a problem.

Mike might know chapter and verse on the subject?

Bob
Image
Information on induction motors here
https://drive.google.com/file/d/0B_GZrX ... sp=sharing
Email:motors@minchin.org.uk
User avatar
9fingers
Old Oak
 
Posts: 3104
Joined: 21 Jul 2014, 20:22
Location: Romsey Hampshire between Southampton and the New Forest
Name: Bob

Re: Hully's Workshop Build - Framing almost complete

Postby Hully » 16 Jan 2017, 15:28

9fingers wrote:I suppose that membrane for roofing does not need to be so strong as that designed for walls as the latter has to support its own weight completely but realistically, for a single storey structure and careful owner-builder use, I cant image there would be a problem.

Mike might know chapter and verse on the subject?

Bob


Thanks for the response Bob.

Both Dan and Mike seem to use the same membrane for both roof and walls so perhaps I'll PM them to check and see what their view on it is.

Cheers
Hully
Hully
Seedling
 
Posts: 39
Joined: 16 Jun 2016, 08:30
Name:

Re: Hully's Workshop Build - Framing almost complete

Postby Hully » 24 Jan 2017, 14:45

Framing is finished!!!...kinda, still need to do the blocking but that doesn't count :D This is how we're looking so far. Ignore the overly long roof joist on the end, it needs to be cut to length.

Image

Pretty happy with it so far, so now onto wrapping the walls in membrane and putting up the battens and trim pieces ready for the cladding which is my next major job.

Cheers
Hully
Last edited by Hully on 26 Jan 2017, 09:54, edited 1 time in total.
Hully
Seedling
 
Posts: 39
Joined: 16 Jun 2016, 08:30
Name:

Re: Hully's Workshop Build - Framing Done!!

Postby Malc2098 » 24 Jan 2017, 15:13

Coming along nicely!
Malcolm
User avatar
Malc2098
Nordic Pine
 
Posts: 853
Joined: 03 Jul 2016, 11:10
Location: Tiverton
Name: Malcolm

Re: Hully's Workshop Build - Framing Done!!

Postby Dan0741 » 24 Jan 2017, 20:33

Hully great work matey. Just a couple of pointers that helped me, and might help you. I faffed about with the window and door trim and should have done what you are doing, ie install at framing stage. However what i would say is that i have moved mine a couple of times for various reasons, door install, cladding etc. On this basis it might be worth screwing and not gluing so you can move them in or out depth wise dependent on other variables before final positioning.

Also bear in mind that the framing you have just finished is the skeleton for the whole structure. I had to install extra framing retrospectively so that I could end up with the cladding fixings in the places I wanted. This applies to both internal and external cladding. One of the bits I missed, and was pointed out by a helpful Terry was the fact that when framing a corner one needs an upright on both aspects that one can screw/nail into. Also if you can help it moving the fixings of your cladding further than 100mm from the cladding ends if you are using timber will be helpful.

I have also retrospectively installed a fireplace in mine, and therefore needed to alter some of the framing to accommodate the hearth etc. It would have been much, much easier to have done this at the time I framed rather than afterwards. Im currently doing the internal cladding, and vapour barrier etc, and had I spent some time thinking all this through first it would have saved me considerable amounts of time.

Im a bit jealous in honesty, I loved the framing stage :mrgreen:

:D
...time is precious; waste it wisely...
Dan0741
Sapling
 
Posts: 328
Joined: 09 Aug 2015, 19:38
Location: nn6
Name: Dan

Re: Hully's Workshop Build - Framing Done!!

Postby Hully » 25 Jan 2017, 09:28

Thanks Gents

Dan - thanks for the advice mate, always gratefully received.

Totally agree on the use of screws/removable fixings for the trim. I had to get the reciprocating saw out a few times to cut through the ring shank nails I was using for the framing so learnt the hard way. I'll use screws wherever possible now that the structure is up and strength isn't the primary concern.

I'd had that thought about additional timbers for fixing trim, cladding etc so I've added in extra noggins in the corners (which you can see in the picture above) to fix the battens, corner boards and internal OSB sheathing. They're on 400mm centres so should provide enough support to stop any flexing in whatever I attach to them.

Not sure I'll be able to nail the cladding 100mm in from the edges but I'd planned on pre-drilling like you did so presumably nailing closer to the edge won't be a problem?

Cheers
Hully
Hully
Seedling
 
Posts: 39
Joined: 16 Jun 2016, 08:30
Name:

Re: Hully's Workshop Build - Framing Done!!

Postby Hully » 25 Jan 2017, 09:48

Just thinking about what I wrote above and it's just dawned on me that the extra noggins will be OK for the corner boards and OSB sheathing but they wont be for the battens as the cladding nails will need to bite into more than just the 20/25mm batten. They need to go through the batten into a stud...

Once the corner boards are up I'll need to work out where the batten nearest the corner will go and then retrospectively add in some additional supports for them...while avoiding tearing the membrane.

Fun times ahead!! :eusa-think:
Hully
Seedling
 
Posts: 39
Joined: 16 Jun 2016, 08:30
Name:

Re: Hully's Workshop Build - Framing Done!!

Postby Tusses » 25 Jan 2017, 12:37

My fav part of any build is the stick framing !
Tusses
Nordic Pine
 
Posts: 857
Joined: 08 May 2016, 10:48
Location: in the middle of the middle
Name:

Re: Hully's Workshop Build - Framing almost complete

Postby Andyp » 25 Jan 2017, 12:44

Hully wrote:Framing is finished!!!...kinda, still need to do the blocking but that doesn't count :D This is how we're looking so far. Ignore the overly long roof joist on the end, it needs to be cut to length.

Image

Pretty happy with it so far, so now onto wrapping the walls in membrane and putting up the battens and trim pieces ready for the cladding which is my next major job.

Cheers
Hully


Hully, I think you may have either moved or deleted this image on photobucket.
cheers

Andy
User avatar
Andyp
Old Oak
 
Posts: 3528
Joined: 22 Jul 2014, 07:05
Location: 14860 Normandy, France
Name: Andy

Re: Hully's Workshop Build - Framing Done!!

Postby Hully » 26 Jan 2017, 09:55

Thanks Andy. I was organising my photos into folders...oops.

I've re-imported the latest photo, new photos will be linked properly.

Cheers
Hully
Hully
Seedling
 
Posts: 39
Joined: 16 Jun 2016, 08:30
Name:

Re: Hully's Workshop Build - Framing Done!!

Postby Andyp » 26 Jan 2017, 12:33

OK Mate,
do you realise that all the earlier photos on the earlier posts have gone the same way?

great progress BTW. You should be right pleased with yourself.
cheers

Andy
User avatar
Andyp
Old Oak
 
Posts: 3528
Joined: 22 Jul 2014, 07:05
Location: 14860 Normandy, France
Name: Andy

Re: Hully's Workshop Build - Framing Done!!

Postby Andyp » 26 Jan 2017, 17:54

Off topic posts relating to organising images on hosting sites moved to Woodmanglers Retreat
cheers

Andy
User avatar
Andyp
Old Oak
 
Posts: 3528
Joined: 22 Jul 2014, 07:05
Location: 14860 Normandy, France
Name: Andy

Previous

Return to Workshop Builds

Who is online

Users browsing this forum: No registered users and 0 guests

cron