The corner of a relatively flimsy building like this is of high importance. If there is any movement there then the building could fail. So, time for some big dovetails:
In hindsight, I should have made the tails slightly smaller, and given the half-pins a bit more guts.
Now, look at the size of those tails, and have a think about the difficulty of transfering the shape onto the end of the "tail board". For a start, there's the issue of holding a 2.2m 5x3 in place whilst marking it. Here's my solution to that:
Then, how do you mark out the tails onto the end-grain? Clearly a small marking knife is no good. I remembered and old shipwright's trick:
This enabled me to get a pencil in flush against the sides:
Then all you have to do is remember that the line isn't in the waste, and cut away:
You can see the saw marks in that last photo from running a tenon saw through the mitre, to get the joint just so. Pointlessly, of course, because that junction will be hidden under a mullion. Obviously, the joint is repeated at the other corner of the building.
More M&Ts, this time on the short side return plates. Everything chopped out by hand of course:
The corner mortices are somewhat different from the others, both in shape, and because they go through two different pieces of wood:
There is the added difficulty that there isn't enough room to use the obvious tool, a coping saw:
I dusted down the jigsaw instead:
Chopping out through the tail wasn't straight forward. I had to wedge stuff into the gap to support the work, otherwise we'd have had bouncing tools and break-out disaster:
But it all worked out in the end:
-
Cock-up! It's quite difficult to remember exactly where you are on the building when you are just working your way through a pile of wood, cutting rebates. There are two different rebates here. One for openings which will have an opening window, and one for openings with fixed glazing. The far end of the building, up against the hedge, will have fixed glazing, but unfortunately I ran the other sized rebate:
I simply planted a piece on. This is going to be the other way up and inside in the final build, so the junction isn't really vulnerable:
Here's a fun variation of the M&Ts, where there is a small rebate (for fixed glazing), and thus all of the mortice is up on the high bit, rather than down at rebate level:
This isn't just a random mullion. This is a mullion with a "down" joint on each end. There are two of these, and they are for the triangle part of the gables. Because I won't be sure of the roof geometry until the frame is erected, I made one of these pieces for each end of the building, and they'll be cut to length to suit the rafter, with a half-lap joint under the rafter:
OK, that's the end of the mullions and wall plates. My next update will cover the cill plates.